BICSI Registered Communications Distribution Designer - RCDD v15 - RCDDv15 Exam Questions
QUESTION NO: 1
66-style connecting blocks (certain designs) can support up to what category of transmission performance?
66-style connecting blocks (certain designs) can support up to what category of transmission performance?
Correct Answer: C
QUESTION NO: 2
An RFQ usually provides more detail than RFP in selection material such as
An RFQ usually provides more detail than RFP in selection material such as
Correct Answer: B
QUESTION NO: 3
What is used to facilitate MINOR changes to the Project Requirements?
Request lot Information (RFI)
What is used to facilitate MINOR changes to the Project Requirements?
Request lot Information (RFI)
Correct Answer: D
QUESTION NO: 4
Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?
Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?
Correct Answer: A
QUESTION NO: 5
The program manager must define the program and understand the organization's target market and customer needs.
What should the program manager do first?
The program manager must define the program and understand the organization's target market and customer needs.
What should the program manager do first?
Correct Answer: B
QUESTION NO: 6
CORRECT TEXT
A program manager joins a team during its preparation phase.
What should the program manager do lo obtain formal sponsor approval to begin the benefits delivery phase1?
CORRECT TEXT
A program manager joins a team during its preparation phase.
What should the program manager do lo obtain formal sponsor approval to begin the benefits delivery phase1?
Correct Answer: B
QUESTION NO: 7
Telecommunications systems typically combine multiple digital data streams into one data stream.
What is this process called?
Telecommunications systems typically combine multiple digital data streams into one data stream.
What is this process called?
Correct Answer: B
QUESTION NO: 8
An ICT distribution designer is providing labeling for a data center room number 2A, located on the second floor having 10 rows of cabinets.
Which of the following identifiers/labels would the designer attach to the bonding and grounding conductor between the first cabinet in the 6th row and the data center ground bar?
An ICT distribution designer is providing labeling for a data center room number 2A, located on the second floor having 10 rows of cabinets.
Which of the following identifiers/labels would the designer attach to the bonding and grounding conductor between the first cabinet in the 6th row and the data center ground bar?
Correct Answer: A
QUESTION NO: 9
Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect
Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect
Correct Answer: C
QUESTION NO: 10
Which two of the following are means in which radiated interference primarily enters electronic devices? (Select two options.)
Which two of the following are means in which radiated interference primarily enters electronic devices? (Select two options.)
Correct Answer: B,E
QUESTION NO: 11
The transfer of unwanted signals may occur over one path or several paths.
What method addresses the mitigation or suppression of unwanted signals?
The transfer of unwanted signals may occur over one path or several paths.
What method addresses the mitigation or suppression of unwanted signals?
Correct Answer: A
QUESTION NO: 12
The program manager completed the program's benefits analysis and planning activities.
What will this ensure tor the program?
The program manager completed the program's benefits analysis and planning activities.
What will this ensure tor the program?
Correct Answer: C
QUESTION NO: 13
Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance
To resolve this situation, which of the following must go through critical review and change"?
Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance
To resolve this situation, which of the following must go through critical review and change"?
Correct Answer: D