BICSI Registered Communications Distribution Designer (RCDD) - RCDDv14 Exam Questions

QUESTION NO: 1
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized the program manager was asked to transition the program into operations.
At this stage, what is expected during the post-review session organized by the program manager?
Correct Answer: C
QUESTION NO: 2
The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost. The program manager has provided monthly performance reports throughout the program's lite cycle.
Which of the following would the customer be interested in reviewing?
Correct Answer: B
QUESTION NO: 3
In a program's definition phase a program manager in country A is assigned to expand a restaurant chain into country B.
The program manager creates the program team by identifying the required protect management resources.
Which of the following represents an initial step needed to evaluate available resources that are aligned with me program's needs''
Correct Answer: B
QUESTION NO: 4
During program execution, how does a program manager ensure that benefits are being realized in accordance with program governance*?
Correct Answer: D
QUESTION NO: 5
The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff What should the program manager do to ensure communications on the component projects are consistent?
Correct Answer: C
QUESTION NO: 6
A company's marketing department Tails an internal compliance audit To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?
Correct Answer: C
QUESTION NO: 7
A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program's benefits sustainment and transition plan What should the program manager do to create this plan?
Correct Answer: A
QUESTION NO: 8
A program receives initial approval from the selection committee to proceed with the program development.
What should the program manager do next"?
Correct Answer: C
QUESTION NO: 9
An ice cream company wants to introduce a new flavor to a new market. The executive sponsor requests a sampling for the test market and the sample group provides negative feedback As this type of program had previously been conducted by the company, the program manager questions whether similar results were experienced during testing.
What should the program manager do next?
Correct Answer: B
QUESTION NO: 10
A program is completed and the expected benefits are realized Before executing the transition and closing of the program, what should the program manager do?
Correct Answer: A
QUESTION NO: 11
An ICT distribution designer is reviewing a client's site information (spaces and pathways) to determine network technology and equipment selection. This is referred to as a___________design process
Correct Answer: A
QUESTION NO: 12
A program manager joins a learn to fix a troubled enterprise-wide customer relationship management (CHM) system Analysis indicates that duplicate customer information data is resulting in redundant client information.
The program manager accesses the knowledge repository tor similar programs to gather historical data and trends. A corrective action is identified, and a change in process is implemented to regain data integrity What should the program manager do with the knowledge gained from this activity?
Correct Answer: D
QUESTION NO: 13
Which two of the following roles do an ICT distribution designer use to ensure a timely and cost-effective telecommunications construction project? (Select two options.)
Correct Answer: D,E
QUESTION NO: 14
The marketing department of a firm has tasked the organization to design a structured cabling system allowing them to support either 10G6aseT or HDBASE-T. The budget requires that only one cable type be installed and that it be MINIMUM compliant. Of the following choices, what is the choice with the MINIMUM solution/solutions for the client?
Correct Answer: A