QUESTION NO: 1
A PV array is installed with a rapid shutdown system per NEC 690.12. The array is 15 feet from the service entrance. What is the maximum voltage allowed within the array boundary 30 seconds after shutdown initiation?
A PV array is installed with a rapid shutdown system per NEC 690.12. The array is 15 feet from the service entrance. What is the maximum voltage allowed within the array boundary 30 seconds after shutdown initiation?
Correct Answer: B
QUESTION NO: 2
A system's inverter efficiency drops from 97% to 94% due to aging. What is the percentage increase in energy loss?
A system's inverter efficiency drops from 97% to 94% due to aging. What is the percentage increase in energy loss?
Correct Answer: C
QUESTION NO: 3
The NEC requires that PV systems installed on dwellings incorporate which of the following components?
The NEC requires that PV systems installed on dwellings incorporate which of the following components?
Correct Answer: A
QUESTION NO: 4
A 10 kW PV system produces 8 kW AC under STC. After one year, output drops to 7.2 kW. What is the most likely maintenance issue?
A 10 kW PV system produces 8 kW AC under STC. After one year, output drops to 7.2 kW. What is the most likely maintenance issue?
Correct Answer: A
QUESTION NO: 5
A module's Voc is 40V at STC. At -5°C with a coefficient of -0.33%/°C, what is the Voc?
A module's Voc is 40V at STC. At -5°C with a coefficient of -0.33%/°C, what is the Voc?
Correct Answer: C
QUESTION NO: 6
In the middle of a winter day, the data acquisition system for a ground-mounted PV system with large central inverters sends an email alert that system performance is at 50% based on irradiance and temperature performance calculations. No inverters are completely offline. The closed technician is a 4-hour drive from the site, and there are no cameras on site. Which is the BEST response to this situation?
In the middle of a winter day, the data acquisition system for a ground-mounted PV system with large central inverters sends an email alert that system performance is at 50% based on irradiance and temperature performance calculations. No inverters are completely offline. The closed technician is a 4-hour drive from the site, and there are no cameras on site. Which is the BEST response to this situation?
Correct Answer: C
QUESTION NO: 7
An installer is working on a 1000V DC PV array. What is the minimum PPE required per NFPA 70E for arc flash protection?
An installer is working on a 1000V DC PV array. What is the minimum PPE required per NFPA 70E for arc flash protection?
Correct Answer: C
QUESTION NO: 8
A system's inverter output is 9 kW at 900 W/m² irradiance. What is the expected output at 1000 W/m²?
A system's inverter output is 9 kW at 900 W/m² irradiance. What is the expected output at 1000 W/m²?
Correct Answer: A
QUESTION NO: 9
A ground-mounted PV system operating with an open-critical voltage of 550V is in a public park. Which installation procedure will meet NEC requirements for protecting the public from potential electric shock?
A ground-mounted PV system operating with an open-critical voltage of 550V is in a public park. Which installation procedure will meet NEC requirements for protecting the public from potential electric shock?
Correct Answer: D
QUESTION NO: 10
A connector not listed to be used in a concealed location and being used as a disconnect for PV equipment shall comply with which of the following?
A connector not listed to be used in a concealed location and being used as a disconnect for PV equipment shall comply with which of the following?
Correct Answer: D
QUESTION NO: 11
A ground resistance measurement on a newly installed grounding electrode indicates a resistance of 130#. The earth connection may be improved by connecting the existing electrode to a:
A ground resistance measurement on a newly installed grounding electrode indicates a resistance of 130#. The earth connection may be improved by connecting the existing electrode to a:
Correct Answer: B
QUESTION NO: 12
A rooftop PV system is proposed for a commercial building with a membrane roof. The structural engineer specifies a maximum allowable dead load of 5 psf. The PV modules weigh 3 psf, and the racking adds 1.5 psf.
What additional load can be added without exceeding the limit?
A rooftop PV system is proposed for a commercial building with a membrane roof. The structural engineer specifies a maximum allowable dead load of 5 psf. The PV modules weigh 3 psf, and the racking adds 1.5 psf.
What additional load can be added without exceeding the limit?
Correct Answer: D
QUESTION NO: 13
An installer is hired to troubleshoot a 10-year-old roottop system with open-circuit voltage of 300V. The ground-fault detection (GFD) device has tripped. The insulation on the exposed source circuit cables has deterlorated with multiple cracks and has no flexibility. Which concern is the MOST likely safely issue when servicing this array?
An installer is hired to troubleshoot a 10-year-old roottop system with open-circuit voltage of 300V. The ground-fault detection (GFD) device has tripped. The insulation on the exposed source circuit cables has deterlorated with multiple cracks and has no flexibility. Which concern is the MOST likely safely issue when servicing this array?
Correct Answer: D
QUESTION NO: 14
A PV system was installed in July 2017 under the 2017 NEC. The system has a string inverter located inside a garage on a wall 10 ft, from the outside wall and 1oft, from the ac load center at the point of utility connection. The PV system has a PV array on the roof. Which of the following represents the PV rapid shutdown system requirement for the controlled PV system conductors associated with this PV array?
A PV system was installed in July 2017 under the 2017 NEC. The system has a string inverter located inside a garage on a wall 10 ft, from the outside wall and 1oft, from the ac load center at the point of utility connection. The PV system has a PV array on the roof. Which of the following represents the PV rapid shutdown system requirement for the controlled PV system conductors associated with this PV array?
Correct Answer: A