QUESTION NO: 1
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 2
How many entities/subcontractors should a scheduled activity cover?
How many entities/subcontractors should a scheduled activity cover?
Correct Answer: C
QUESTION NO: 3
What day would Activity C complete if the duration of Activity B was reduced to zero?
What day would Activity C complete if the duration of Activity B was reduced to zero?
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 4
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity
2002?
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity
2002?
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 5
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?

Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?

Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 6
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 7
Should you verify the as-built schedule before proceeding with a schedule analysis?
Should you verify the as-built schedule before proceeding with a schedule analysis?
Correct Answer: C
QUESTION NO: 8
A KPI is an acronym for:
A KPI is an acronym for:
Correct Answer: D
QUESTION NO: 9
If Activity E's duration changes to 4 months, what is the overall duration of the project.

If Activity E's duration changes to 4 months, what is the overall duration of the project.

Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 10
What is the remaining work duration of Active D?

What is the remaining work duration of Active D?

Correct Answer: D
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 11
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 12
Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?
Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?
Correct Answer: A
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 13
Identify the late finish to develop plans and specs.

Identify the late finish to develop plans and specs.

Correct Answer: B