live chatMcAfee Secure sites help keep you safe from identity theft, credit card fraud, spyware, spam, viruses and online scams
Pass4Test 10%OFF Discount Code

ASIS Physical Security Professional - PSP Exam Questions

QUESTION NO: 1
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 2
How many entities/subcontractors should a scheduled activity cover?
Correct Answer: C
QUESTION NO: 3
What day would Activity C complete if the duration of Activity B was reduced to zero?
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 4
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity
2002?
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 5
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 6
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 7
Should you verify the as-built schedule before proceeding with a schedule analysis?
Correct Answer: C
QUESTION NO: 8
A KPI is an acronym for:
Correct Answer: D
QUESTION NO: 9
If Activity E's duration changes to 4 months, what is the overall duration of the project.
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 10
What is the remaining work duration of Active D?
Correct Answer: D
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 11
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 12
Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?
Correct Answer: A
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 13
Identify the late finish to develop plans and specs.
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).