CompTIA Project+ - PK0-400 Exam Questions
QUESTION NO: 1
The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?
The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?
Correct Answer: D
QUESTION NO: 2
Which of the following is a schedule that illustrates the duration of an activity?
Which of the following is a schedule that illustrates the duration of an activity?
Correct Answer: B
QUESTION NO: 3
Which of the following are examples of organizational change? (Choose two.)
Which of the following are examples of organizational change? (Choose two.)
Correct Answer: B,D
QUESTION NO: 4
A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?
A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?
Correct Answer: D
QUESTION NO: 5
Which of the following activities are associated with the closing phase of a project? (Choose two.)
Which of the following activities are associated with the closing phase of a project? (Choose two.)
Correct Answer: A,C
QUESTION NO: 6
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success.
Which of the following risk strategies should the project manager adopt?
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success.
Which of the following risk strategies should the project manager adopt?
Correct Answer: C
QUESTION NO: 7
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items?
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items?
Correct Answer: B
QUESTION NO: 8
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Correct Answer: D
QUESTION NO: 9
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
Correct Answer: B
QUESTION NO: 10
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?
Correct Answer: A