QUESTION NO: 1
The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?
Correct Answer: D
QUESTION NO: 2
Which of the following is a schedule that illustrates the duration of an activity?
Correct Answer: B
QUESTION NO: 3
Which of the following are examples of organizational change? (Choose two.)
Correct Answer: B,D
QUESTION NO: 4
A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?
Correct Answer: D
QUESTION NO: 5
Which of the following activities are associated with the closing phase of a project? (Choose two.)
Correct Answer: A,C
QUESTION NO: 6
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success.
Which of the following risk strategies should the project manager adopt?
Correct Answer: C
QUESTION NO: 7
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items?
Correct Answer: B
QUESTION NO: 8
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Correct Answer: D
QUESTION NO: 9
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
Correct Answer: B
QUESTION NO: 10
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?