live chatMcAfee Secure sites help keep you safe from identity theft, credit card fraud, spyware, spam, viruses and online scams
Pass4Test 10%OFF Discount Code

Microsoft Managing Microsoft Dynamics Implementations - MB5-858 Exam Questions

QUESTION NO: 1
Sure Step provides multiple ways to manage project documents. Which options allow you to collaborate more effectively and efficiently?
Choose the 2 that apply.
Correct Answer: A,C
QUESTION NO: 2
Your company is preparing a proposal for a large and complex implementation that will require significant customizations in an enterprise organization. One of the elements that you plan to address is testing and creating a test plan. When is the best time to create a high-level test plan that includes the general standards and procedures that must be followed when conducting software testing and validation?
Correct Answer: A
QUESTION NO: 3
You are planning a meeting at the end of the Analysis phase that highlights the current health of the project, key milestones achieved, key deliverables completed, project level issues and risks, and the conditions of satisfaction assessment. This meeting will be the 'sign-off' of the Analysis phase.
Which Sure Step document do you prepare for this meeting?
Correct Answer: B
QUESTION NO: 4
As an application consultant, you specialize in the configuration of Microsoft Dynamics solutions. Using the Sure Step Requirements and Configuration Cross-Phase, when should you begin your configuration activities?
Correct Answer: B
QUESTION NO: 5
You are the consultant on a Microsoft Dynamics NAV 2009 implementation. You need to review the
benefits of a Scoping Assessment with the customer.
Which benefits of a Scoping Assessment might you discuss?
Choose the 2 that apply.
Correct Answer: A,C
QUESTION NO: 6
Your team needs to implement a Microsoft Dynamics solution for a large enterprise business that has complex business requirements and four globally distributed sites. Although each site has unique business needs, the company wants to implement a uniform solution across all sites.
Which implementation approach does Sure Step typically recommend?
Correct Answer: D
QUESTION NO: 7
You are managing a complex, multisite project under a fixed price contract. Your customer wants to refine the project scope. You agree that the changes are appropriate, but believe that they constitute a major change that increases the project scope.
What should you do?
Correct Answer: A
QUESTION NO: 8
You are considering training the customer's core Implementation team before starting the business process analysis.
How is the goal of this training different from training in the upcoming phases?
Correct Answer: D
QUESTION NO: 9
As part of the Scoping Assessment and Statement Of Work, you have identified the following:
-
The implementation is for a single location
-
The implementation requires two ISV solutions
-
Business requirements include customization of medium complexity.
You need to analyze the customer's current and future business strategies.
What should you do?
Correct Answer: C
QUESTION NO: 10
The sales team wants to close the sales process. They need to make sure that the scope and all other recommendations for project execution are analyzed, documented, and agreed upon by the customer. They are now looking for documentation that defines the formal services agreement and outlines the engagement in enough detail that they can make a decision.
Which document can the sales team use to support the implementation proposal?
Correct Answer: C