ISEB Foundation Certificate in Project Management - ISEB-PM1 Exam Questions
QUESTION NO: 1
In which of the following contract types is a price ceiling set and any additional costs above the price ceiling becomes the responsibility of the performing organization?
In which of the following contract types is a price ceiling set and any additional costs above the price ceiling becomes the responsibility of the performing organization?
Correct Answer: C
QUESTION NO: 2
A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.
A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.
Correct Answer: D
QUESTION NO: 3
Many companies self insure against some risk. Problems which can arise from self- insurance include:
Many companies self insure against some risk. Problems which can arise from self- insurance include:
Correct Answer: C
QUESTION NO: 4
What are the identified risks for doing excessive decomposition in a WBS?
What are the identified risks for doing excessive decomposition in a WBS?
Correct Answer: A
QUESTION NO: 5
Extensive use of ___ communication is MOST likely to aid in solving complex problems.
Extensive use of ___ communication is MOST likely to aid in solving complex problems.
Correct Answer: B
QUESTION NO: 6
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Correct Answer: C
QUESTION NO: 7
You have assembled your thoughts into a message. As you pass this information to a second party, you are giving this person your:
You have assembled your thoughts into a message. As you pass this information to a second party, you are giving this person your:
Correct Answer: E
QUESTION NO: 8
Which of the following is a strategy for positive risks?
Which of the following is a strategy for positive risks?
Correct Answer: C
QUESTION NO: 9
You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following?
You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following?
Correct Answer: D
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 10
Employee unions would most likely satisfy which level in Maslow's hierarchy of needs?
Employee unions would most likely satisfy which level in Maslow's hierarchy of needs?
Correct Answer: E
QUESTION NO: 11
You are a project manager of ABC organization. You are estimating the project in initiation phase. What level of accuracy you can expect?
You are a project manager of ABC organization. You are estimating the project in initiation phase. What level of accuracy you can expect?
Correct Answer: D
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 12
Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?
Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?
Correct Answer: C
QUESTION NO: 13
Formal written correspondence is mandated in which of the following situations:
Formal written correspondence is mandated in which of the following situations:
Correct Answer: C
QUESTION NO: 14
Which statement is TRUE about Present Value(PV)?
Which statement is TRUE about Present Value(PV)?
Correct Answer: A