SAP Certified Specialist - SAP Activate for Cloud Solutions Project Manager - E-ACTCLD-23 Exam Questions
QUESTION NO: 1
Custom Code Management process in SAP Solution Manager provides which of the following capabilities?
Custom Code Management process in SAP Solution Manager provides which of the following capabilities?
Correct Answer: A,B,C
QUESTION NO: 2
Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4HANA Implementation?
There are 3 answers to this question.
Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4HANA Implementation?
There are 3 answers to this question.
Correct Answer: B,C,E
QUESTION NO: 3
What kind of user is enabled by SAP Cloud ALM for operations to identify disruptions and react to them?
Note: There are 2 answers to this question.
What kind of user is enabled by SAP Cloud ALM for operations to identify disruptions and react to them?
Note: There are 2 answers to this question.
Correct Answer: B,C
QUESTION NO: 4
What is the basis for approving work results (signing Act of Acceptance) on Project Phase level?
What is the basis for approving work results (signing Act of Acceptance) on Project Phase level?
Correct Answer: B
QUESTION NO: 5
What are the three elements of SAP Activate? There are 3 correct answers to this question.
What are the three elements of SAP Activate? There are 3 correct answers to this question.
Correct Answer: B,C,D
QUESTION NO: 6
What is the best transition scenario for a customer looking for some, but not full process redesign, and re-use of existing processes in some areas that still fit?
What is the best transition scenario for a customer looking for some, but not full process redesign, and re-use of existing processes in some areas that still fit?
Correct Answer: C
QUESTION NO: 7
What are the Transition Paths to SAP S/4HANA?
What are the Transition Paths to SAP S/4HANA?
Correct Answer: A,B,C
QUESTION NO: 8
In which phase do you run the user acceptance test?
In which phase do you run the user acceptance test?
Correct Answer: C
QUESTION NO: 9
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition.
What is the sequence of selected key deliverables across the project phases? Please choose the answer.
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition.
What is the sequence of selected key deliverables across the project phases? Please choose the answer.
Correct Answer: N
QUESTION NO: 10
What are some of the benefits that apply to SAP Cloud ALM as a cloud product? Note: There are 2 answers to this question.
What are some of the benefits that apply to SAP Cloud ALM as a cloud product? Note: There are 2 answers to this question.
Correct Answer: B,D
QUESTION NO: 11
What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition? Please choose the correct answer.
What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition? Please choose the correct answer.
Correct Answer: A
QUESTION NO: 12
How many change projects can be active at a time?
How many change projects can be active at a time?
Correct Answer: A
QUESTION NO: 13
What are some activities the project team will perform in executing project work during the Explore Phase?
What are some activities the project team will perform in executing project work during the Explore Phase?
Correct Answer: A,D,E
QUESTION NO: 14
Where can you find Integration Content? 3 correct answers
Where can you find Integration Content? 3 correct answers
Correct Answer: A,B,C
QUESTION NO: 15
How do you achieve frequent checkpoints with the end user in an Agile delivery approach? There are 2 answers to this question.
How do you achieve frequent checkpoints with the end user in an Agile delivery approach? There are 2 answers to this question.
Correct Answer: B,C