QUESTION NO: 1
Which assignments can be made for the organizational object Purchasing Organization? (Choose two)
Correct Answer: B,C
QUESTION NO: 2
You want to change the valuation class of a material. The system does not permit this
change.
Which of the following answers describe possible reasons?
There are 3 correct answers to this question.
Response:
Correct Answer: B,C,D
QUESTION NO: 3
Which attribute is an influencing factor for the field selection of materials in SAP Materials Management?
Please choose the correct answer.
Response:
Correct Answer: D
QUESTION NO: 4
You want to post a goods issue from blocked stock.
In which of the following cases is this possible?
Correct Answer: B
QUESTION NO: 5
What can be changed in a material document after it has been posted?
Please choose the correct answer.
Response:
Correct Answer: A
QUESTION NO: 6
Which times belong to the replenishment lead time in the planning run for an externally procured material?
There are 3 correct answers to this question.
Response:
Correct Answer: B,C,D
QUESTION NO: 7
Which procurement elements can be created in Purchasing with automatic purchase order generation? (Choose two)
Correct Answer: A,C
QUESTION NO: 8
Which of the following belong to the static lot-sizing procedure? (Choose three)
Correct Answer: B,D,E
QUESTION NO: 9
In Customizing for Logistics Invoice Verification, the following values are defined for the
stochastic block:
Threshold value - 10000
Percentage - 50
You enter an invoice with a value of 15000.
What is the probability that the invoice will be blocked stochastically?
Please choose the correct answer.
Response:
Correct Answer: A
QUESTION NO: 10
Which criteria can you select to create the invoices automatically for invoicing plans?
There are 3 correct answers to this question.
Response:
Correct Answer: B,D,E
QUESTION NO: 11
What is the relationship between a service master record and a service specification in SAP Materials Management?
Please choose the correct answer.
Response:
Correct Answer: B
QUESTION NO: 12
When the procurement process is without a material master in SAP Materials
Management, which configuration element do you assign to the valuation class?
Please choose the correct answer.
Response:
Correct Answer: C