SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing 2021 - C_TS422_2021 Exam Questions

QUESTION NO: 1
In your project, you have several materials that are planned by different people. How can you assign the planning responsibility?
Correct Answer: A
QUESTION NO: 2
What does a line hierarchy in repetitive manufacturing represent?
Correct Answer: C
QUESTION NO: 3
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Correct Answer: A,B,D
QUESTION NO: 4
Which standard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.
Correct Answer: B,C
QUESTION NO: 5
Which times elements does MRP consider in backward scheduling to determine he order dates for components from dependent requirements?
Correct Answer: A,D
QUESTION NO: 6
What do you use to dispatch operations from planned orders so that the production plan can be fulfilled?
Correct Answer: A
QUESTION NO: 7
What is the purpose of a reporting point confirmation in repetitive manufacturing?
Correct Answer: B,C
QUESTION NO: 8
When working with bouth cross-plant and plant-specific material statuses n the material master, which statuses has the higest priority?
Correct Answer: B
QUESTION NO: 9
Which of the following questions do you have to answer before you start creating a BOM?
Correct Answer: A,D