SAP Certified Application Associate - Project System with SAP ERP 6.0 EHP4 - C_TPLM22_64 Exam Questions

QUESTION NO: 1
Which of the following allows you to view project objects with key performance data for quick analysis and update the percentage complete for earned value calculations?
Please choose the correct answer.
Response:
Correct Answer: D
QUESTION NO: 2
When the system derives settlement rules, it generates profitability segments that contain the characteristic values of which of the following assigned to them?
There are 2 correct answers to this question.
Response:
Correct Answer: A,B
QUESTION NO: 3
In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?
Please choose the correct answer.
Response:
Correct Answer: D
QUESTION NO: 4
In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as?
Please choose the correct answer.
Response:
Correct Answer: D
QUESTION NO: 5
Which of the following can be used to calculate and update interest in SAP project system?
There are 2 correct answers to this question.
Response:
Correct Answer: A,B
QUESTION NO: 6
Which of the following statements about milestone billing are correct?
There are 3 correct answers to this question.
Response:
Correct Answer: B,D,E
QUESTION NO: 7
Which of the following are controlled using plant and order type parameters?
There are 2 correct answers to this question.
Response:
Correct Answer: B,C
QUESTION NO: 8
How can you determine the degree of control yourself if you are managing material in plant stock or according to individual WBS element where you have no control over procurement or fully responsible for procurement?
Please choose the correct answer.
Response:
Correct Answer: C