QUESTION NO: 1
What does discharge confirm under the FIDIC Red Book (edition 1999)?
What does discharge confirm under the FIDIC Red Book (edition 1999)?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 2
Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)
Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 3
FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?
FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?
Correct Answer: A
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 4
Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?
Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 5
Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?
Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?
Correct Answer: D
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 6
You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition
2017), with Time for Completion of 5 months.
The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
What is the correct Commencement Date?
You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition
2017), with Time for Completion of 5 months.
The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
What is the correct Commencement Date?
Correct Answer: A
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 7
The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.
The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.
Correct Answer: A
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 8
You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition
2017). The project had been suspended due to a material change in the Employer ' s financial arrangement.
You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?
You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition
2017). The project had been suspended due to a material change in the Employer ' s financial arrangement.
You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).