QUESTION NO: 1
Which of the following situations occur when a production order is set to Technically Complete (TECO)?
(Choose three.)
Correct Answer: B,D,E
QUESTION NO: 2
Which of the following functions does SAP Supply Chain Management (SCM) offer?
Correct Answer: A
QUESTION NO: 3
The stock/requirements list for a finished product contains only one sales order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date for the fixed planned order is set to a later date than the one for the sales order.
However, a corresponding rescheduling exception message does not appear.
What could be the reasons? (Choose two)
Correct Answer: A,D
QUESTION NO: 4
You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.
What do you have to consider in this scenario?
Correct Answer: B
QUESTION NO: 5
Which of the following statements about the planning functions available in SAP ECC is correct?
Correct Answer: D
QUESTION NO: 6
Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)
Correct Answer: A,B,C
QUESTION NO: 7
Which of the following elements can be used in a process order? (Choose three)