QUESTION NO: 1
What do you choose when creating a new network by copying an operative network?
There are 3 correct answers to this question.
Response:
What do you choose when creating a new network by copying an operative network?
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
QUESTION NO: 2
Which of the following information regarding cost activity is not relevant for the calculation of planned costs?
Please choose the correct answer.
Response:
Which of the following information regarding cost activity is not relevant for the calculation of planned costs?
Please choose the correct answer.
Response:
Correct Answer: A
QUESTION NO: 3
Which of the following helps you to adjust cost planning to changing circumstances during the execution phase of the project?
Please choose the correct answer.
Response:
Which of the following helps you to adjust cost planning to changing circumstances during the execution phase of the project?
Please choose the correct answer.
Response:
Correct Answer: C
QUESTION NO: 4
Which function of budgeting allows you to transfer any funds not used up in the previous fiscal year to the budget of the new fiscal year?
Please choose the correct answer.
Response:
Which function of budgeting allows you to transfer any funds not used up in the previous fiscal year to the budget of the new fiscal year?
Please choose the correct answer.
Response:
Correct Answer: C
QUESTION NO: 5
If the available user-definable fields do not satisfy your requirement, you have an option to develop additional fields for which of the following.
There are 2 correct answers to this question.
Response:
If the available user-definable fields do not satisfy your requirement, you have an option to develop additional fields for which of the following.
There are 2 correct answers to this question.
Response:
Correct Answer: C,D
QUESTION NO: 6
Based on which of the following; reservations or purchase requisitions can automatically be created for a project?
There are 2 correct answers to this question.
Response:
Based on which of the following; reservations or purchase requisitions can automatically be created for a project?
There are 2 correct answers to this question.
Response:
Correct Answer: B,C
QUESTION NO: 7
In which type of billing do you assign the posting to the down payment request when you post the incoming payment for a down payment?
Please choose the correct answer.
Response:
In which type of billing do you assign the posting to the down payment request when you post the incoming payment for a down payment?
Please choose the correct answer.
Response:
Correct Answer: C
QUESTION NO: 8
In Structure Information System which transactions allow you to analyze and edit the entire hierarchical structure of a project including documents, PS texts, networks, other orders, investment programs, and SD documents?
There are 2 correct answers to this question.
Response:
In Structure Information System which transactions allow you to analyze and edit the entire hierarchical structure of a project including documents, PS texts, networks, other orders, investment programs, and SD documents?
There are 2 correct answers to this question.
Response:
Correct Answer: A,B
QUESTION NO: 9
You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?
Please choose the correct answer.
Response:
You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?
Please choose the correct answer.
Response:
Correct Answer: A
QUESTION NO: 10
How can you distinguish between service activities and external activities while accessing the detailed information for service activities on the external tab page?
There are 2 correct answers to this question.
Response:
How can you distinguish between service activities and external activities while accessing the detailed information for service activities on the external tab page?
There are 2 correct answers to this question.
Response:
Correct Answer: B,D
QUESTION NO: 11
When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following?
There are 2 correct answers to this question.
Response:
When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following?
There are 2 correct answers to this question.
Response:
Correct Answer: A,D
QUESTION NO: 12
You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS).
However, once you enter the WBS element and the working hours in CATS you receive an error message.
What could be the reason?
Please choose the correct answer.
Response:
You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS).
However, once you enter the WBS element and the working hours in CATS you receive an error message.
What could be the reason?
Please choose the correct answer.
Response:
Correct Answer: A
QUESTION NO: 13
A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend?
There are 2 correct answers to this question.
Response:
A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend?
There are 2 correct answers to this question.
Response:
Correct Answer: A,C
QUESTION NO: 14
What are the three areas of the project screen?
There are 3 correct answers to this question.
Response:
What are the three areas of the project screen?
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D