QUESTION NO: 1
Which action should be completed by the Pittville Project Board?
Correct Answer: C
QUESTION NO: 2
Answer the following questions about the benefits realization strategy, framework and plans that have been drafted for the Pittville project.
Decide whether the entry is appropriate for the document identified and select the responses that support your decision.
Remember to select 2 answers to each question.
The Management Case states that the Western Area Learning Improvements Programme Director is ultimately responsible for:
1. Delivering the benefits of the Pittville project
2. Ensuring arrangements have been made to realize the benefits.
Which 2 statements apply to these entries?
Correct Answer: A,B
QUESTION NO: 3
The Local Education Authority Director has been appointed as the Senior Responsible Owner for the Western Area Learning Improvement Programme.
Which action is MOST appropriate for this role?
Correct Answer: B
QUESTION NO: 4
Springbank School has been hugely oversubscribed so has decided to expand its further education unit. It is working formally with Battledown School to reduce course duplication and to potentially offer a greater range of education courses. The Governors from Springbank School feel that these scheduled changes need to be reflected in the Pittville project FBC, even though Springbank was not a shortlisted option.
Should the FBC be updated with the Springbank changes?
Correct Answer: A
QUESTION NO: 5
The Local Education Authority Director has agreed to be the Senior Responsible Owner. Therefore, they are ultimately responsible for the realization of benefits resulting from the Pittville project.
Should the responsibilities for the benefits realization arrangements be documented in the Economic Case?
Correct Answer: D
QUESTION NO: 6
Using the Scenario and the extract below from the Revenue Budget for the Pittville project, answer the following questions. (Note. The figures entered are correct).

Which 2 observations correctly evaluate the Expenditure?
Correct Answer: A,B
QUESTION NO: 7
Using the Scenario, answer the following questions about the critical success factors (CSFs) for the option to build a campus on the Old Fire Station Headquarters site, with all courses for 16 - 18-year-olds provided by Pittville University.
Remember to select 2 answers to each question.
Which 2 attributes demonstrate that this option supports the key CSF Strategic fit and business needs?
Correct Answer: D,E
QUESTION NO: 8
Which statement should be recorded under the Post Project Evaluation heading?
Correct Answer: B
QUESTION NO: 9
Answer the following questions about the actions taken when preparing the Economic Case within the Full Business Case (FBC).

Decide whether the action taken represents an appropriate application of the Five Case Model for this project and select the response that supports your decision.
Since approval of the OBC, there has been an attractive bid for the Old Fire Station Headquarters site by a supermarket company.
The bid is 15% higher than the original amount that the site was valued at.
Should the FBC production be delayed while the ranking of the options in the OBC is reassessed?
Correct Answer: D
QUESTION NO: 10
Providing better facilities, improving learning provision and offering a wider choice of education courses.
Which of the key objectives for spend are these objectives based on?
Correct Answer: D