Autodesk Certified Professional in BIM Management for Building Design - BIM_MGT_101 Exam Questions

QUESTION NO: 1
The BIM manager received a subcontractor's 3D model containing specialty equipment to be integrated into the federated model. Upon review, they observe that:
Many elements lack consistent object styles and category assignments.
Some components are modelled with excessive detail, affecting performance.
Embedded data does not follow the project's naming conventions outlined in the BEP.
What is the most appropriate next step when evaluating this geometry and content?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 2
During a weekly BIM health review, the BIM manager compares two versions of the same architectural Revit model submitted one month apart. The newer model's file size has doubled, synchronization time has increased by 40%, and users report sluggish performance. A model audit reveals no major geometry changes, but warnings have increased from 600 to 750, and several Civil CAD files are now imported.
What is the most likely root cause of the model performance degradation?
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 3
A BIM manager is preparing to onboard a group of subcontractors into Autodesk Forma for a large healthcare project. These subcontractors need access to a limited set of model files related only to interior partitions, but should not be able to view or modify structural, MEP, or scheduling content.
What two actions should the BIM manager take to manage data security in this scenario? (Select two.)
Correct Answer: B,E
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 4
An AEC company has received a design model from the Architect of Record to begin creating construction documentation. The BIM Execution Plan identifies a fast-track delivery schedule, and the project team includes new consultants with limited exposure to the client's preferred toolset and workflows. The BIM manager must determine how best to prepare the delivery team and assess the model's compatibility with internal systems.
As the BIM manager prepares for the Project Kickoff meeting, which two pieces of information are most critical to avoid issues related to digital compatibility? (Select two.)
Correct Answer: B,D
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 5
Refer to the exhibit.

Upon opening a model, the following warnings saying "Room Tag is outside of its Room" appear.
What action should the BIM manager ask the design team to take in order to identify any Room Tags that need a leader because the tag may be too big to fit within the room?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 6
During a coordination meeting, project leads ask for a report showing only active clashes between mechanical systems and structural framing in patient-room zones, following the approved clash matrix.
What is the most effective way to provide this report using Model Coordination?
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).