Adobe Workfront Project Manager Professional - AD0-E903 Exam Questions
QUESTION NO: 1
The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.
Which report grants the executive team this visibility?
The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.
Which report grants the executive team this visibility?
Correct Answer: A
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 2
A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?
A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 3
What are two ways to associate milestone steps to tasks? (Choose two.)
What are two ways to associate milestone steps to tasks? (Choose two.)
Correct Answer: A,C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 4
A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?
A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 5
A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.
Which date type would the project manager utilize?
A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.
Which date type would the project manager utilize?
Correct Answer: A
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 6
Which group of project elements can be used to monitor an active project's progress?
Which group of project elements can be used to monitor an active project's progress?
Correct Answer: A
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 7
A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?
A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?
Correct Answer: C
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 8
A project manager is assigned to a new Workfront request. The request specifies that the management team's sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?
A project manager is assigned to a new Workfront request. The request specifies that the management team's sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?
Correct Answer: A
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).