Oracle Manufacturing Cloud 2020 Implementation Essentials - 1z0-1075-20 Exam Questions

QUESTION NO: 1
Your customer has defined the work definitions. They have created and saved a new version for the work definition and want to edit that work definition.
Which two attributes cannot be updated using the Edit Work Definition Details action?
Correct Answer: A,B
QUESTION NO: 2
The Manufacturing Engineer, responsible for creating and maintaining the Work Definitions, has scheduled the Process Item Structure Changes to Work Definitions program. However, after the execution of the program the engineer did not receive a notification with the details of the Item Structure changes.
Which two reasons could cause this?
Correct Answer: A,C
QUESTION NO: 3
Identify two conditions that should be met at the same time for a Standard Operation to be called an Optional Operation.
Correct Answer: D,E
QUESTION NO: 4
Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
Correct Answer: B
QUESTION NO: 5
The production user wants to report Work Order completion.
Identify two ways of reporting the progress of work order at work order operation level.
Correct Answer: A,E
QUESTION NO: 6
A production Operator is executing work order in your plant. After completing move transactions, he notices that he has performed some incorrect move operations, including incorrect scrap and reject transactions. He is required to perform a reverse transaction to correct the errors. The operations are not count point enabled and not auto charged.
Identify the four transactions to correct this situation.
Correct Answer: A,B,C,E