live chatMcAfee Secure sites help keep you safe from identity theft, credit card fraud, spyware, spam, viruses and online scams
Pass4Test 10%OFF Discount Code

Microsoft Managing Projects and Portfolios with Microsoft PPM - 070-348 Exam Questions

QUESTION NO: 1
HOTSPOT
You are a project manager in a large organization. During the project, some tasks have slipped, but the dependencies are still valid.
You are reviewing the project's Gantt chart.

Use the drop-down menus to select the answer choice that answers each question.
Correct Answer:
QUESTION NO: 2
A company is using Microsoft PPM to track task progress. The company implements standard overtime and non-billable time tracking.
You observe that you cannot enter overtime hours in your current timesheet.
You need to ensure that you can enter overtime hours.
What should you do?
Correct Answer: A
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 3
Your company has had several large projects fail due to cost overruns and the lack of available resources. These projects use an enterprise project type named Large IT Project and use a workflow to govern the approval of the projects. The workflow consists of four phases: Initiate, Plan, Execute, and Close.
You need to use Microsoft PPM to compare the value that a new project provides with the cost of implementing the project.
Which three configuration changes should you make? Each correct answer presents part of the solution.
Correct Answer: B,E,F
QUESTION NO: 4
You are a resource manager in an organization that uses Microsoft PPM for resource management. You manage two teams, one local and one remote. Project managers are instructed to always submit resource requests based on generic roles instead of named resources. Resource managers replace the generic resources with available named resources.
Project managers must not start work on projects that have generic resources assigned.
You need to replace proposed requests with committed, named resources.
Which three actions should you perform? Each correct answer presents part of the solution.
Correct Answer: B,C,D
QUESTION NO: 5
DRAG DROP
You are the administrator for an organization that uses Microsoft PPM.
Users must be able to create projects by using predefined templates.
You need to create a new Enterprise Project Template and make it available for users.
In which order should you perform the actions? To answer, move all of the actions from the list of actions to the answer area and arrange them in the correct order.
Correct Answer: