live chatMcAfee Secure sites help keep you safe from identity theft, credit card fraud, spyware, spam, viruses and online scams
Pass4Test 10%OFF Discount Code

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - C_TS422_2020 Exam Questions

QUESTION NO: 1
An issue storage location was NOT found through the work center, bill of material (BOM)item, or material master. What determines whether the storage location can be derived from the production version?
Correct Answer: A
QUESTION NO: 2
How can SAP S/4HANA support a GMP compliant production process? Note: There are 3 correct answers to this question.
Correct Answer: C,D,E
QUESTION NO: 3
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.
Correct Answer: B,D
QUESTION NO: 4
What is the difference between co-products and by-products?
Correct Answer: C
QUESTION NO: 5
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
Correct Answer: A
QUESTION NO: 6
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?
Correct Answer: B