SAP Certified Associate - SAP Activate Project Manager - C_ACTIVATE05 Exam Questions
QUESTION NO: 1
Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition?
There are 3 correct answers to this question.
Response:
Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition?
There are 3 correct answers to this question.
Response:
Correct Answer: B,C,D
QUESTION NO: 2
In which phase do you create a prioritized list of user requirements?
Please choose the correct answer.
Response:
In which phase do you create a prioritized list of user requirements?
Please choose the correct answer.
Response:
Correct Answer: D
QUESTION NO: 3
In which phase of the SAP Activate methodology does the team complete the Transformation Planning?
Please choose the correct answer.
Response:
In which phase of the SAP Activate methodology does the team complete the Transformation Planning?
Please choose the correct answer.
Response:
Correct Answer: A
QUESTION NO: 4
When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?
Please choose the correct answer.
Response:
When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?
Please choose the correct answer.
Response:
Correct Answer: D
QUESTION NO: 5
When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
Response:
When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
Response:
Correct Answer: D
QUESTION NO: 6
How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
Response:
How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
Response:
Correct Answer: A
QUESTION NO: 7
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition. What is the correct sequence of selected key deliverables across the project phases?
Please choose the correct answer.
Response:
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition. What is the correct sequence of selected key deliverables across the project phases?
Please choose the correct answer.
Response:
Correct Answer: O
QUESTION NO: 8
What do you do during Sprint Execution?
Please choose the correct answer.
Response:
What do you do during Sprint Execution?
Please choose the correct answer.
Response:
Correct Answer: B