QUESTION NO: 1
What is the difference between the "system conversion" and the "new implementation OF SAP S/4HANA transaction path. There are 2 correct option to this question.
What is the difference between the "system conversion" and the "new implementation OF SAP S/4HANA transaction path. There are 2 correct option to this question.
Correct Answer: A,D
QUESTION NO: 2
Which of the following content best outlines the scope of the Integration Test?
Please choose the correct answer.
Response:
Which of the following content best outlines the scope of the Integration Test?
Please choose the correct answer.
Response:
Correct Answer: B
QUESTION NO: 3
What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of SAP Activate?
Please choose the correct answer.
Response:
What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of SAP Activate?
Please choose the correct answer.
Response:
Correct Answer: A
QUESTION NO: 4
How do you achieve frequent checkpoints with the end user in an Agile delivery approach? There are 2 correct answers to this question.
How do you achieve frequent checkpoints with the end user in an Agile delivery approach? There are 2 correct answers to this question.
Correct Answer: A,C
QUESTION NO: 5
When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
Response:
When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
Response:
Correct Answer: D
QUESTION NO: 6
What are some extension item types can be transported from the Quality system to the Production system?
What are some extension item types can be transported from the Quality system to the Production system?
Correct Answer: A,B,C,E
QUESTION NO: 7
How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
Response:
How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
Response:
Correct Answer: A
QUESTION NO: 8
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase?
There are 3 correct answers to this question.
Response:
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase?
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D
QUESTION NO: 9
Which of the following are not phases of the SAP Activate methodology? There are 2 correct answers to this question.
Which of the following are not phases of the SAP Activate methodology? There are 2 correct answers to this question.
Correct Answer: B,C
QUESTION NO: 10
In which SAP Activate methodology phase does the team complete the Transformation Strategy? Please choose the correct answer.
In which SAP Activate methodology phase does the team complete the Transformation Strategy? Please choose the correct answer.
Correct Answer: B
QUESTION NO: 11
Which of the following is true about a cloud implementation project? There are 2 correct answers to this question.
Which of the following is true about a cloud implementation project? There are 2 correct answers to this question.
Correct Answer: B,D
QUESTION NO: 12
In what respect is SAP Activate Methodology different from the ASAP Methodology?
Please choose the correct answer.
Response:
In what respect is SAP Activate Methodology different from the ASAP Methodology?
Please choose the correct answer.
Response:
Correct Answer: B
QUESTION NO: 13
Which new project roles are introduced with the SAP Activate Agile methodology?
There are 2 correct answers to this question.
Response:
Which new project roles are introduced with the SAP Activate Agile methodology?
There are 2 correct answers to this question.
Response:
Correct Answer: A,C
QUESTION NO: 14
Which of the following SAP S/4HANA Landscape Transformation options are enabled? There are 3 correct answers to this question.
Which of the following SAP S/4HANA Landscape Transformation options are enabled? There are 3 correct answers to this question.
Correct Answer: B,C,D