QUESTION NO: 1
A customer asks for your recommendation regarding this requirement:
1. We plan to have a Data Guard Configuration with one primary database and one physical standby database.
2. We want zero data loss in case of a disaster involving the loss of one component.
3. We want to do Real Application Testing occasionally on the Standby Database.
Which solution, if any, satisfies these requirements?
A customer asks for your recommendation regarding this requirement:
1. We plan to have a Data Guard Configuration with one primary database and one physical standby database.
2. We want zero data loss in case of a disaster involving the loss of one component.
3. We want to do Real Application Testing occasionally on the Standby Database.
Which solution, if any, satisfies these requirements?
Correct Answer: B
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 2
Which two statements are true regarding asynchronous redo transport in a Data Guard
Which two statements are true regarding asynchronous redo transport in a Data Guard
Correct Answer: A,D
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 3
Suppose that you manage the following databases in your environment:
* boston: Primary database with a single PDB called DEVI
* london: Physical standby database protecting the PDB called DEVI
* orcl: Stand-alone database with a single PDB called PDB1 as a remote clone source You are planning to run the following command to create a remote clone in the primary database (boston) using pdbi in orcl:
Which are the THREE prerequisites for automating instantiation of the PDB in the standby database (london)?
Suppose that you manage the following databases in your environment:
* boston: Primary database with a single PDB called DEVI
* london: Physical standby database protecting the PDB called DEVI
* orcl: Stand-alone database with a single PDB called PDB1 as a remote clone source You are planning to run the following command to create a remote clone in the primary database (boston) using pdbi in orcl:
Which are the THREE prerequisites for automating instantiation of the PDB in the standby database (london)?
Correct Answer: C,D,E
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 4
You created two remote physical standby databases using SQL and RMAN.
The primary database is a four-instance RAC database and each physical standby database has two instances.
Roles-based services are used for client connectivity and have been defined in the Grid Infrastructure.
Consider these operational requirements:
* The ability to manage multiple standby databases with a single tool
* The simplification of switchovers, failovers, reinstatements, and conversions to and from snapshot standby databases
* The automation of failovers to a specified target standby database
Which TWO tools can be used to fulfill these requirements7
You created two remote physical standby databases using SQL and RMAN.
The primary database is a four-instance RAC database and each physical standby database has two instances.
Roles-based services are used for client connectivity and have been defined in the Grid Infrastructure.
Consider these operational requirements:
* The ability to manage multiple standby databases with a single tool
* The simplification of switchovers, failovers, reinstatements, and conversions to and from snapshot standby databases
* The automation of failovers to a specified target standby database
Which TWO tools can be used to fulfill these requirements7
Correct Answer: B,E
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 5
Which THREE are true about using flashback database in a Data Guard environment?
Which THREE are true about using flashback database in a Data Guard environment?
Correct Answer: C,D,E
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 6
Which four requirements can be met by deploying a logical standby database?
Which four requirements can be met by deploying a logical standby database?
Correct Answer: A,B,C,F
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 7
Examine this query and its output:

Which two statements are true?
Examine this query and its output:

Which two statements are true?
Correct Answer: C,D
Explanation: Only visible for Pass4Test members. You can sign-up / login (it's free).
QUESTION NO: 8
Your Data Guard environment has a remote physical standby database with real-time query enabled, which is used for reporting, and a logical standby database used for DSS reporting.
Switchovers or failovers are possible due to testing or in case of a disaster.
Clients use local TNSNAMES.ORA files to define connection strings to the database instances.
Which three will prevent clients from connecting to the wrong database instances?
Your Data Guard environment has a remote physical standby database with real-time query enabled, which is used for reporting, and a logical standby database used for DSS reporting.
Switchovers or failovers are possible due to testing or in case of a disaster.
Clients use local TNSNAMES.ORA files to define connection strings to the database instances.
Which three will prevent clients from connecting to the wrong database instances?
Correct Answer: A,B,G